BU-GGC - The design, supply, installation and commissioning of a compost production line.

The RFT has ended, you cannot answer the invitation.

A new build compost production line, in accordance with the HVC’ Program of Requirements, consisting of a new: a) pre-treatment line for the “Vegetable, Fruit and Garden waste" (VFG); b) mixing line and; c) after-treatment line. Note: The existing composting hall remains, the new build CPL shall have some mechanical, electrical and automation interfaces with the units of the existing installations.

Works

19-5-2023 00:00:00

45253800-3  Composting plant construction work
45213280-9  Construction works for compost facility


HVC Groep
Jadestraat 1
1812 RD
Alkmaar
Netherlands
View profile


http://www.hvcgroep.nl

Published notices
Contract notice (TenderNed) 20-4-2023 15:01
Contract or concession award notice – standard regime (eForm) 11-3-2025 08:44 Original notice publication
Packages
The design, supply, installation and commissioning of a compost production line.