The Scope of work for COBRAcable VSC Converter includes design, execution and completion of the following: — HVDC-VSC Converter substation in Eemshaven, The Netherlands. — HVDC-VSC Converter substation in Endrup, Denmark. The transfer capability for the COBRAcable VSC Converter Plant shall be 700 MW at +/- 320kV DC with reference to IEC TR 62543:2013 Ed. 1.1 High- voltage direct current (HVDC) power transmission using voltage sourced converters (VSC)
30-12-2014 10:00:00
31121110-4 Power converters
31200000-8 Electricity distribution and control apparatus
45315300-1 Electricity supply installations
50532000-3 Repair and maintenance services of electrical machinery, apparatus and associated equipment
51120000-9 Installation services of mechanical equipment
Energinet
Tonne Kjærsvej 65
7000
Fredericia
Denmark
View profile
Kirsten Ebstrup
https://eu.eu-supply.com/ctm/supplier/publictenders?B=ENERGINET
| Notice | Date of dispatch |
|---|---|
| Contract Notice (This site) | 10-12-2014 21:10 |
| Contract notice - utilities (TED (v208)) | 11-12-2014 11:10 |
Notice for additional information, information on incomplete procedure or corrigendum (TED (v208))
|
11-12-2014 11:10 |