The scope of works includes, in particular, design, delivery, execution and completion of the following: - 2x 25 km 3 core 150 kV Submarine Cable - Transport and laying of the 150 kV Submarine Cables - Pull-in onto Kriegers Flak E (KFE) and Baltic 2 platforms - Delivery and installation of endterminations for the cables on the KFE and Baltic 2 platforms - Related services The transfer capability for the Submarine Cable is supposed to be in the range of about 400 MW. The relevant details will be specified in the tender documents
18-11-2015 12:00:00
31321500-7 Submarine cable
Energinet
Tonne Kjærsvej 65
7000
Fredericia
Denmark
View profile
Eva Damsted Juhler
https://eu.eu-supply.com/ctm/supplier/publictenders?B=ENERGINET
| Notice | Date of dispatch |
|---|---|
| Contract notice - utilities (TED (v208)) | 27-10-2015 15:40 |
Notice for additional information, information on incomplete procedure or corrigendum (TED (v208))
|
03-11-2015 10:40 |
| 06. Contract award notice - utilities (TED (v209)) | 29-12-2016 11:40 |