The objective of this study is the technical and economic feasibility of a carbon capture facility for the waste CHP plant owned and operated by Fjernvarme Fyn Affald A/S (FFA). FFA receives approximately 280.000 t/year of mixed waste and consequently the captured CO2 will be a mix of fossil and biogenic CO2. The major part of the biogenic CO2 is assumed to be utilized by Fortum for methanol production to the extent that this is feasible (to be investigated by Fortum in separate study) whereas not utlised CO2 shall be stored permanently.
23-01-2023 13:00:00
71318000-0 Byggtekniska konsulttjänster och rådgivning
71600000-4 Teknisk provning, analys och konsulttjänster
90713000-8 Miljörådgivning
Fjernvarme Fyn
Havnegade 120
5000
Odense C
Danmark
Jette Køhler
https://www.fjernvarmefyn.dk/
| Annons | Utsändningsdatum |
|---|---|
| 05.Meddelande om upphandling – försörjningssektorerna (TED (v209)) | 06-01-2023 11:27 |
| 06. Meddelande om tilldelning av kontrakt – försörjningssektorerna (TED (v209)) | 25-08-2023 00:12 |