CTM
Instructions:
Here are all documents for specified package. Some documents are available to download without the need to logon.
Documents - Package 371737:1 - E39 Rogfast. Entreprise E03 – Hovedtunneler, Harestad – entreprisegrense E03/E02
Document available to download
Size (kB)
11000-e03.zip
10236
11000-e03.zip
8717
11000-e03_Tunnel.sfi
9168
11000-e03_Tunnel.sfi
9168
12000-e03.zip
4830
12000-e03.zip
5062
12000-e03_Tunnel.sfi
10300
12000-e03_Tunnel.sfi
10300
14 - NA-rundskriv-2006-11 - Vegoppmerking.pdf
385
14 - Vedlegg til NA-rundskriv_2006-11.pdf
461
20_24789-5 Rettet-utslippstillatelse---Rogfast-E03 14933195_1_1.PDF
607
20_24789-5 Rettet-utslippstillatelse---utslipp-av-renset-anleggsvann-og-vaskevann-fra-Rogfast 14933196_1_1.PDF
69
30000.zip
159
30000.zip
159
30000_Tunnel_e03.sfi
70
30000_Tunnel_e03.sfi
70
30050.zip
773
30050.zip
773
90100.zip
814
90100.zip
814
90200.zip
111
90200.zip
111
Addendum 1.docx
16
AKU01_Anleggsstøy_Mekjarvik-Harestad_03.pdf
15826
D1_E03_Boknafjorden-sør_2022-02-15.gab
8500
D1_E03_Boknafjorden-sør_2022-02-15.pdf
2067
D1_E03_Boknafjorden-sør_2022-02-15.xml
3573
D1_E03_Boknafjorden-sør_2022-06-15.gab
8496
D1_E03_Boknafjorden-sør_2022-06-15.pdf
2108
D1_E03_Boknafjorden-sør_2022-06-15.xml
3622
D1_E03_Boknafjordtunnelen-sør_2022-09-20.gab
8496
D1_E03_Boknafjordtunnelen-sør_2022-09-20.pdf
3431
D1_E03_Boknafjordtunnelen-sør_2022-09-20.xml
3624
D1_E03_Boknafjordtunnelen-sør_2022-10-20.gab
8500
D1_E03_Boknafjordtunnelen-sør_2022-10-20.pdf
3413
D1_E03_Boknafjordtunnelen-sør_2022-10-20.xml
3599
D1_E03_Vedleggsliste_addendum 05.pdf
178
D1_E03_Vedleggsliste_addendum 06.pdf
117
E03 Beregning klimagassutslipp for utvalgte innsatsfaktorer.xlsm
52
E03 Beregning klimagassutslipp for utvalgte innsatsfaktorer_rev_1.xlsm
52
E03 Beregning klimagassutslipp for utvalgte innsatsfaktorer_rev_2.xlsm
52
E03 Beregning klimagassutslipp for utvalgte innsatsfaktorer_rev_3-rettelse.xlsm
52
E03 Vedlegg liste over fagmodeller.pdf
115
E03 Vedlegg liste over fagmodeller.pdf
297
E03 Vedlegg liste over fagmodeller.pdf
297
E03 Vedlegg liste over grunnlagsmodeller.pdf
75
E03 Vedlegg liste over grunnlagsmodeller.pdf
75
E03_ABCDE.pdf
1933
E03_ABCDE.pdf
1757
E03_ABCDE_2022-06-17.pdf
1755
E03_ABCDE_addendum 5.pdf
1737
E03_ABCDE_addendum 6.pdf
1553
E03_A-tegninger.pdf
5782
E03_A-tegninger.pdf
5792
E03_A-tegninger.pdf
5792
E03_B-tegninger.pdf
38912
E03_B-tegninger.pdf
38912
E03_C-tegninger.pdf
4865
E03_C-tegninger.pdf
4725
E03_D-tegninger.pdf
1120
E03_D-tegninger.pdf
1107
E03_D-tegninger.pdf
1104
E03_E1.docx
489
E03_E1.docx
489
E03_E2-2.docx
65
E03_E2-2.docx
65
E03_E2-3.docx
64
E03_E2-3.docx
64
E03_E2-3.docx
60
E03_F-tegninger.pdf
5491
E03_F-tegninger.pdf
5535
E03_GH-tegninger.pdf
9337
E03_GH-tegninger.pdf
9502
E03_IN-tegninger.pdf
711
E03_IN-tegninger.pdf
656
E03_I-tegninger.pdf
7506
E03_I-tegninger.pdf
7515
E03_J-tegninger.pdf
27147
E03_J-tegninger.pdf
27162
E03_J-tegninger.pdf
27248
E03_K-tegninger_dagsone.pdf
14428
E03_K-tegninger_dagsone.pdf
14013
E03_K-tegninger_tunnel.pdf
16849
E03_K-tegninger_tunnel.pdf
16923
E03_L-tegninger.pdf
17260
E03_L-tegninger.pdf
17130
E03_N-tegninger.pdf
191
E03_N-tegninger.pdf
191
E03_O-tegninger.pdf
648
E03_O-tegninger.pdf
620
E03_V-tegninger.pdf
18033
E03_V-tegninger.pdf
17947
E03_V-tegninger.pdf
17946
E03_Y-tegninger.pdf
399
E03_Y-tegninger.pdf
399
E03_Z-tegninger.pdf
10700
E03_Z-tegninger.pdf
10759
E03_Z-tegninger.pdf
11831
E2.8 Prisskjema E03-Dagsone Harestad.xlsx
36
E2.8 Prisskjema E03-Dagsone Harestad.xlsx
37
E2.8 Skilt- og mengdeliste_Dagsone Harestad.pdf
235
E2.8 Skilt- og mengdeliste_Dagsone Harestad.pdf
160
Fastmerkerapport for E39 Rogfast_okt2021.pdf
774
fm_ark_e03_k42.ifc
736
fm_ark_e03_k42.ifc
736
fm_bommer_e03_harestad-dagsone.ifc
28
fm_bommer_e03_harestad-dagsone.ifc
19
fm_bommer_e07_harestad-dagsone.ifc
57
fm_bommer_e07_harestad-dagsone.ifc
47
fm_driftsåpning_e03_harestad-dagsone.ifc
24
fm_elektro_e03_k42.ifc
59
fm_elektro_e03_k42.ifc
59
fm_elektro_e07_k42.ifc
29
fm_elektro_e07_k42.ifc
29
fm_geo_e03_forskjæring-harestad.dwg
552
fm_geo_e03_forskjæring-harestad.dwg
552
fm_geo_e03_forskjæring-harestad.ifc
1329
fm_geo_e03_forskjæring-harestad.ifc
1329
fm_geo_e03_fylling-mekjarvik.dwg
633
fm_geo_e03_fylling-mekjarvik.dwg
633
fm_geo_e03_fylling-mekjarvik.ifc
741
fm_geo_e03_fylling-mekjarvik.ifc
741
fm_geo_e03_fylling-mekjarvik-sjete.dwg
793
fm_geo_e03_fylling-mekjarvik-sjete.dwg
793
fm_geo_e03_fylling-mekjarvik-sjete.ifc
6375
fm_geo_e03_fylling-mekjarvik-sjete.ifc
6375
fm_kabel_e03_belysning.dwg
4002
fm_kabel_e03_belysning.ifc
827
fm_kabel_e03_belysning.ifc
828
fm_kabel_e03_føringsveier.dwg
19879
fm_kabel_e03_føringsveier.ifc
45659
fm_kabel_e03_føringsveier.ifc
52603
fm_kabel_e03_fordeling.dwg
899
fm_kabel_e03_fordeling.ifc
32
fm_kabel_e03_fordeling.ifc
32
fm_kabel_e07_fordeling.ifc
111
fm_kabel_e07_fordeling.ifc
257
fm_konst_e03_k40-k41.ifc
44802
fm_konst_e03_k40-k41.ifc
40772
fm_konst_e03_k42.ifc
23358
fm_konst_e03_k42.ifc
23358
fm_landskap_e03_gjerde.dwg
1321
fm_landskap_e03_gjerde.dwg
1334
fm_landskap_e03_gjerde.ifc
4263
fm_landskap_e03_gjerde.ifc
3434
fm_landskap_e03_terreng.dwg
7169
fm_landskap_e03_terreng.dwg
5624
fm_landskap_e03_terreng.ifc
2784
fm_landskap_e03_terreng.ifc
1943
fm_miljø_e03_anleggsgrense.dwg
1431
fm_miljø_e03_anleggsgrense.dwg
1431
fm_miljø_e03_anleggsgrense.dwg
824
fm_miljø_e03_hensynssoner.dwg
2508
fm_miljø_e03_hensynssoner.dwg
2508
fm_miljø_e03_hensynssoner.dwg
2013
fm_miljø_e03_inngjerding.dwg
792
fm_miljø_e03_inngjerding.dwg
792
fm_miljø_e03_kulturminner_anleggsfase.dwg
138
fm_miljø_e03_kulturminner_anleggsfase.dwg
138
fm_miljø_e03_utslippspunkt.dwg
2480
fm_miljø_e03_utslippspunkt.dwg
2480
fm_oppmerking_e03_tunnel.ifc
7501
fm_oppmerking_e03_tunnel.ifc
7377
fm_oppmerking_e03-portalsone.ifc
117
fm_skilt_e03_harestad-dagsone.ifc
224
fm_skilt_e03_harestad-dagsone.ifc
152
fm_skilt_e07_harestad-dagsone.ifc
196
fm_skilt_e07_harestad-dagsone.ifc
161
fm_tunnel_e03_bankett_L11-L12.ifc
16584
fm_tunnel_e03_bankett_L11-L12.ifc
15685
fm_tunnel_e03_bankett_L11-L12_portalsone.ifc
128
fm_tunnel_e03_bankett_L11-L12_portalsone.ifc
130
fm_tunnel_e03_j21-j22_L11-L12.ifc
50424
fm_tunnel_e03_j21-j22_L11-L12.ifc
54580
fm_tunnel_e03_j21-j22_L11-L12.ifc
54580
fm_tunnel_e03_j27_hildringshall_L11-L12.ifc
221620
fm_tunnel_e03_j27_hildringshall_L11-L12.ifc
184505
fm_tunnel_e03_j27_splitthall_installasjoner_L11.ifc
36205
fm_tunnel_e03_j27_splitthall_installasjoner_L11.ifc
34282
fm_tunnel_e03_j27_splitthall_installasjoner_L12.ifc
39595
fm_tunnel_e03_j27_splitthall_installasjoner_L12.ifc
37682
fm_tunnel_e03_j27_splitthall_splittbuer_L11 .ifc
417916
fm_tunnel_e03_j27_splitthall_splittbuer_L11 .ifc
417916
fm_tunnel_e03_j27_splitthall_splittbuer_L12.ifc
417916
fm_tunnel_e03_j27_splitthall_splittbuer_L12.ifc
417916
fm_tunnel_e03_jording_L11-L12.ifc
33007
fm_tunnel_e03_jording_L11-L12.ifc
32179
fm_tunnel_e03_jording_L11-L12.ifc
32082
fm_tunnel_e03_jording_L11-L12_portalsone.ifc
50
fm_tunnel_e03_jording_L11-L12_portalsone.ifc
43
fm_tunnel_e03_k23_L11-L12.ifc
23328
fm_tunnel_e03_k24_TB1102.ifc
23341
fm_tunnel_e03_k24_TB1102.ifc
22882
fm_tunnel_e03_K24_TB1102_armering.ifc
25893
fm_tunnel_e03_K24_TB1102_armering.ifc
30204
fm_tunnel_e03_k24_TB1103.ifc
23341
fm_tunnel_e03_k24_TB1103.ifc
22882
fm_tunnel_e03_k24_TB1104.ifc
23341
fm_tunnel_e03_k24_TB1104.ifc
23256
fm_tunnel_e03_k24_TB1105.ifc
23341
fm_tunnel_e03_k24_TB1105.ifc
22882
fm_tunnel_e03_k24_TB1106.ifc
23341
fm_tunnel_e03_k24_TB1106.ifc
23256
fm_tunnel_e03_k24_TB1107.ifc
23341
fm_tunnel_e03_k24_TB1107.ifc
22882
fm_tunnel_e03_k24_TB1171.ifc
21766
fm_tunnel_e03_k24_TB1171.ifc
21723
fm_tunnel_e03_k24_TB1172.ifc
21766
fm_tunnel_e03_k24_TB1172.ifc
21723
fm_tunnel_e03_k24_TB1202.ifc
23832
fm_tunnel_e03_k24_TB1202.ifc
23541
fm_tunnel_e03_k24_TB1203.ifc
23832
fm_tunnel_e03_k24_TB1203.ifc
23541
fm_tunnel_e03_k24_TB1204.ifc
23832
fm_tunnel_e03_k24_TB1204.ifc
23902
fm_tunnel_e03_k24_TB1205.ifc
23832
fm_tunnel_e03_k24_TB1205.ifc
23541
fm_tunnel_e03_k24_TB1206.ifc
23832
fm_tunnel_e03_k24_TB1206.ifc
23902
fm_tunnel_e03_k24_TB1207.ifc
23832
fm_tunnel_e03_k24_TB1207.ifc
23542
fm_tunnel_e03_k25_PS1101.ifc
1251
fm_tunnel_e03_k25_PS1101.ifc
1248
fm_tunnel_e03_k25_PS1102.ifc
5610
fm_tunnel_e03_k25_PS1102.ifc
4829
fm_tunnel_e03_k25_PS1102_konsollvegg.ifc
487
fm_tunnel_e03_k25_PS1102_konsollvegg.ifc
487
fm_tunnel_e03_k25_PS1103.ifc
1251
fm_tunnel_e03_k25_PS1103.ifc
1248
fm_tunnel_e03_k25_PS1104.ifc
1251
fm_tunnel_e03_k25_PS1104.ifc
1248
fm_tunnel_e03_k25_PS1105.ifc
18052
fm_tunnel_e03_k25_PS1105.ifc
18027
fm_tunnel_e03_k25_PS1105_konsollvegg.ifc
89
fm_tunnel_e03_k25_PS1105_konsollvegg.ifc
89
fm_tunnel_e03_k25_PS1106.ifc
12392
fm_tunnel_e03_k25_PS1106.ifc
12353
fm_tunnel_e03_k25_PS1106_konsollvegg.ifc
90
fm_tunnel_e03_k25_PS1106_konsollvegg.ifc
90
fm_tunnel_e03_k25_PS1121.ifc
9914
fm_tunnel_e03_k25_PS1121.ifc
9316
fm_tunnel_e03_k25_PS1121_konsollvegg.ifc
92
fm_tunnel_e03_k25_PS1121_konsollvegg.ifc
92
fm_tunnel_e03_k26_PS1101.ifc
12193
fm_tunnel_e03_k26_PS1101.ifc
12184
fm_tunnel_e03_k26_PS1102.ifc
12193
fm_tunnel_e03_k26_PS1102.ifc
12184
fm_tunnel_e03_k26_PS1103.ifc
12193
fm_tunnel_e03_k26_PS1103.ifc
12184
fm_tunnel_e03_k26_PS1104.ifc
12193
fm_tunnel_e03_k26_PS1104.ifc
12184
fm_tunnel_e03_k30-31.ifc
970
fm_tunnel_e03_k30-31.ifc
970
fm_tunnel_e03_kabelstige_L11-L12.ifc
78814
fm_tunnel_e03_kabelstige_L11-L12.ifc
78814
fm_tunnel_e03_kabelstige_L11-L12_portalsone.ifc
661
fm_tunnel_e03_kabelstige_L11-L12_portalsone.ifc
661
fm_tunnel_e03_oppheng_trafikkstyring_L11-L12.ifc
230912
fm_tunnel_e03_oppheng_trafikkstyring_L11-L12.ifc
230968
fm_tunnel_e03_oppheng_trafikkstyring_L11-L12_portalsone.ifc
4797
fm_tunnel_e03_oppheng_trafikkstyring_L11-L12_portalsone.ifc
4798
fm_tunnel_e03_sprengning_L11-L12.ifc
306272
fm_tunnel_e03_sprengning_L11-L12.ifc
306184
fm_tunnel_e03_sprengning_L11-L12_portalsone.ifc
2030
fm_tunnel_e03_sprengning_L11-L12_portalsone.ifc
2030
fm_tunnel_e03_tekniske-installasjoner_L11-L12.ifc
385185
fm_tunnel_e03_tekniske-installasjoner_L11-L12.ifc
383373
fm_tunnel_e03_tekniske-installasjoner_L11-L12.ifc
507029
fm_tunnel_e03_trekkerør_grøfter_L11-L12.ifc
6781
fm_tunnel_e03_trekkerør_grøfter_L11-L12.ifc
6781
fm_tunnel_e03_trekkerør_L11-12.ifc
180048
fm_tunnel_e03_trekkerør_L11-12.ifc
173722
fm_tunnel_e03_trekkerør_L11-12.ifc
173727
fm_tunnel_e03_trekkerør_L11-12_portalsone.ifc
210
fm_tunnel_e03_trekkerør_L11-12_portalsone.ifc
184
fm_tunnel_e03_trekkerør-installasjoner_L11-L12.ifc
37590
fm_tunnel_e03_trekkerør-installasjoner_L11-L12.ifc
36509
fm_tunnel_e03_va_grøfter_L11-L12.ifc
186566
fm_tunnel_e03_va_grøfter_L11-L12.ifc
186577
fm_tunnel_e03_va_grøfter_L11-L12_portalsone.ifc
8584
fm_tunnel_e03_va_grøfter_L11-L12_portalsone.ifc
10654
fm_tunnel_e03_VF-sikring_L11-L12.ifc
27935
fm_tunnel_e03_VF-sikring_L11-L12.ifc
27935
fm_tunnel_e07_k24_TB1102.ifc
22
fm_tunnel_e07_k24_TB1102.ifc
22
fm_tunnel_e07_k24_TB1103.ifc
22
fm_tunnel_e07_k24_TB1103.ifc
22
fm_tunnel_e07_k24_TB1104.ifc
22
fm_tunnel_e07_k24_TB1104.ifc
22
fm_tunnel_e07_k24_TB1105.ifc
22
fm_tunnel_e07_k24_TB1105.ifc
22
fm_tunnel_e07_k24_TB1106.ifc
22
fm_tunnel_e07_k24_TB1106.ifc
22
fm_tunnel_e07_k24_TB1107.ifc
22
fm_tunnel_e07_k24_TB1107.ifc
22
fm_tunnel_e07_k24_TB1202.ifc
33
fm_tunnel_e07_k24_TB1202.ifc
22
fm_tunnel_e07_k24_TB1203.ifc
33
fm_tunnel_e07_k24_TB1203.ifc
22
fm_tunnel_e07_k24_TB1204.ifc
33
fm_tunnel_e07_k24_TB1204.ifc
22
fm_tunnel_e07_k24_TB1205.ifc
33
fm_tunnel_e07_k24_TB1205.ifc
22
fm_tunnel_e07_k24_TB1206.ifc
33
fm_tunnel_e07_k24_TB1206.ifc
22
fm_tunnel_e07_k24_TB1207.ifc
33
fm_tunnel_e07_k24_TB1207.ifc
22
fm_tunnel_e07_k25_PS1101.ifc
469
fm_tunnel_e07_k25_PS1101.ifc
469
fm_tunnel_e07_k25_PS1102.ifc
468
fm_tunnel_e07_k25_PS1102.ifc
468
fm_tunnel_e07_k25_PS1103.ifc
469
fm_tunnel_e07_k25_PS1103.ifc
469
fm_tunnel_e07_k25_PS1104.ifc
469
fm_tunnel_e07_k25_PS1104.ifc
469
fm_tunnel_e07_k25_PS1105.ifc
2201
fm_tunnel_e07_k25_PS1105.ifc
2201
fm_tunnel_e07_k25_PS1106.ifc
2134
fm_tunnel_e07_k25_PS1106.ifc
2134
fm_tunnel_e07_k25_PS1121.ifc
1222
fm_tunnel_e07_k25_PS1121.ifc
1222
fm_tunnel_e07_k25_pumper_PS1101.ifc
9695
fm_tunnel_e07_k25_pumper_PS1101.ifc
9695
fm_tunnel_e07_k25_pumper_PS1102.ifc
9695
fm_tunnel_e07_k25_pumper_PS1102.ifc
9695
fm_tunnel_e07_k25_pumper_PS1103.ifc
9695
fm_tunnel_e07_k25_pumper_PS1103.ifc
9695
fm_tunnel_e07_k25_pumper_PS1104.ifc
9695
fm_tunnel_e07_k25_pumper_PS1104.ifc
9695
fm_tunnel_e07_k25_pumper_PS1105.ifc
18212
fm_tunnel_e07_k25_pumper_PS1105.ifc
18212
fm_tunnel_e07_k25_pumper_PS1106.ifc
17988
fm_tunnel_e07_k25_pumper_PS1106.ifc
17988
fm_tunnel_e07_k25_pumper_PS1121.ifc
9181
fm_tunnel_e07_k25_pumper_PS1121.ifc
9181
fm_tunnel_e07_k26_PS1101.ifc
1372
fm_tunnel_e07_k26_PS1101.ifc
1372
fm_tunnel_e07_k26_PS1102.ifc
1372
fm_tunnel_e07_k26_PS1102.ifc
1372
fm_tunnel_e07_k26_PS1103.ifc
1372
fm_tunnel_e07_k26_PS1103.ifc
1372
fm_tunnel_e07_k26_PS1104.ifc
1372
fm_tunnel_e07_k26_PS1104.ifc
1372
fm_tunnel_e07_tekniske-installasjoner.ifc
51959
fm_tunnel_e07_tekniske-installasjoner.ifc
51962
fm_tunnel_e07_trafikkstyring_L11_L12.ifc
86806
fm_tunnel_e07_trafikkstyring_L11_L12.ifc
86985
fm_tunnel_e07_trafikkstyring_L11_L12_portalsone.ifc
225
fm_tunnel_e07_trafikkstyring_L11_L12_portalsone.ifc
225
fm_va_e03_tunnel.ifc
34191
fm_va_e03_tunnel.ifc
30186
fm_va_e03_tunnel_portalsone.ifc
3849
fm_va_e03_tunnel_portalsone.ifc
3605
fm_veg_e03_dagsone_11000.ifc
5565
fm_veg_e03_dagsone_11000.ifc
1935
fm_veg_e03_dagsone_12000.ifc
1388
fm_veg_e03_dagsone_12000.ifc
1139
fm_veg_e03_dagsone_30000.ifc
502
fm_veg_e03_dagsone_30000.ifc
502
fm_veg_e03_dagsone_30050.ifc
1862
fm_veg_e03_dagsone_30050.ifc
1862
fm_veg_e03_dagsone_90100.ifc
4988
fm_veg_e03_dagsone_90100.ifc
4988
fm_veg_e03_dagsone_90200.ifc
761
fm_veg_e03_dagsone_90200.ifc
761
fm_veg_e03_portalsone_11000.ifc
686
fm_veg_e03_portalsone_11000.ifc
686
fm_veg_e03_portalsone_12000.ifc
1178
fm_veg_e03_portalsone_12000.ifc
1178
fm_veg_e03_tunnel_11000.ifc
41661
fm_veg_e03_tunnel_11000.ifc
41661
fm_veg_e03_tunnel_12000.ifc
41507
fm_veg_e03_tunnel_12000.ifc
41507
fm_vegutstyr_e03_3d.dwg
2834
fm_vegutstyr_e03_3d.dwg
5383
fm_vegutstyr_e03_3d.ifc
5596
fm_vegutstyr_e03_3d.ifc
3445
fm_vvs_e03_k42.ifc
1598
fm_vvs_e03_k42.ifc
1598
gm_eks_e03_kabler.dwg
24528
gm_eks_e03_kabler.dwg
24528
gm_eks_e03_linjer.dwg
493
gm_eks_e03_linjer.dwg
493
gm_innmåling_E03-Mekjarvik_3d_eksist.dwg
63720
gm_innmåling_E03-Mekjarvik_3d_eksist.dwg
63720
gm_kart_e03_diverse_3d.dwg
977
gm_kart_e03_diverse_3d.dwg
977
gm_kart_e03_terrengoverflate_3d.dwg
46399
gm_kart_e03_terrengoverflate_3d.dwg
46399
gm_VA_eksist_e03_mekjarvik.dwg
992
Informasjon.docx
15
NavisWorks bruksanvisning.pdf
1138
NavisWorks bruksanvisning.pdf
1138
NO-026-YM Potetcystenematodeprøvetaking Randaberg.pdf
1793
NO-056-YM Utslippssøknad anleggsvann og vann i driftsfase Rogfast E03 Boknafjordtunnel Sør m vedlegg.pdf
26372
NO-085-GEO E03 Utfylling i sjø Mekjarvik.pdf
9616
NO-088-GEO.pdf
2154
NO-091-GEO_Datarapport.pdf
29448
NO-124-TUN Kjøresterke porter i tunnel.pdf
1253
NO-161-YM Miljøsaneringsbeskrivelse og avfallsplan Harestadveien 41.pdf
4508
Notat addendum 2.pdf
68
Notat addendum 3.pdf
66
Notat addendum 4.pdf
135
Notat addendum 5.pdf
179
Notat addendum 6.pdf
65
PS1101-D1_tunnel.sfi
41
PS1101-D1_tunnel.sfi
41
PS1101-D2_tunnel.sfi
10
PS1101-D2_tunnel.sfi
10
PS1101-P_tunnel.sfi
391
PS1101-P_tunnel.sfi
391
PS1105-D1_tunnel.sfi
643
PS1105-D1_tunnel.sfi
643
PS1105-D2_Tunnel.sfi
19
PS1105-D2_Tunnel.sfi
19
PS1106-D1_tunnel.sfi
712
PS1106-D1_tunnel.sfi
712
PS1106-S_tunnel.sfi
15
PS1106-S_tunnel.sfi
15
PS1121-D1_tunnel.sfi
359
PS1121-D1_tunnel.sfi
370
PS1121-D2_tunnel.sfi
43
PS1121-D2_tunnel.sfi
43
PS1121-D3_tunnel.sfi
28
PS1121-D3_tunnel.sfi
28
Randaberg kommune - FV 521 - gnr 49 bnr 12 - midlertidig avkjørsel i forbindelse med bygging av Rogfast - Vedtak.pdf
450
Referat E03 Tilbudskonferanse.docx
46
Søknad-Vedlegg 2.pdf.pdf
526
Seismikk evaluerings rapport for E13 Rogfast kombinert med forside.pdf
40770
SHA-plan E03 Rogfast.pdf
862
Spørsmål ID 197124.docx
273
TB11-P02255_tunnel.sfi
37
TB11-P02255_tunnel.sfi
37
TF11-P01320_Tunnel.sfi
141
TF11-P01320_Tunnel.sfi
141
TF11-P02250_Tunnel.sfi
787
TF11-P02250_Tunnel.sfi
787
Tilbudskonferanse Byggeleder E03 Rogfast-Fredrik.pdf
700
Tilbudskonferanse Geologi E03 Rogfast-Øyvind Riste.pdf
1107
Tilbudskonferanse Klima E03 Rogfast-Hilde.pdf
993
Tilbudskonferanse Prosjektering E03 Rogfast-HIRL.pdf
628
Tilbudskonferanse Prosjektleder - E03 - Oddvar.pdf
1983
Tilbudskonferanse YM E03 Rogfast-Merete.pdf
1947
Tillatelse til utfylling i sjø - Rogfast E03 - 50 4, Mekjarvik i Randaberg kommune - Statens vegvesen Region vest.PDF
1545
tm_dagsone_E03.nwd
40561
tm_dagsone_E03.nwd
44677
tm_dagsone_E03.nwd
45708
tm_tunnel_E03.nwd
264102
tm_tunnel_E03.nwd
271053
tm_tunnel_E03.nwd
281680
TR12-P02003_Tunnel.sfi
30
TR12-P02003_Tunnel.sfi
30
Tunnelbyggetid 2021 - E03 Boknafjordtunnelen sør_2.pdf
544
Tunnelbyggetid 2021 - E03 Boknafjordtunnelen sør_3.pdf
1798
Utforming avkjørsel for lastbil og vogntog (1).pdf
288
Utfyllingssøknad i sjø E03 Mekjarvik, E39 Rogfast.pdf
276
Vedlegg 1.pdf
11961
Vedlegg 1-03-Z01-411.pdf
3996
Vedlegg 10-RIM01 Turbiditetsmålinger Byfjorden ved testdropp_J02.pdf
3004
Vedlegg 11 - NO-030-YM Rapport E 39 Rogfast Mekjarvik D04.pdf
758
Vedlegg 12 - Niva rapport 6856 - 2015 - Modellering av strøm og partikkeltransport i Mekjarvik.pdf
8358
Vedlegg 13 - SHA_YM-084 Mekjarvik sedimentundersøkelse_J01.pdf
1395
Vedlegg 14 - Testforsøk lekterdropp, sluttkontroll E11 - Plast.pdf
73
Vedlegg 15 - NO-129-YM Overvåkningprogram Byfjorden ifb utfylling i sjø E11.pdf
666
Vedlegg 16 - NO-110-YM Rogfast - geologi i tunneltraséen og metallinnhold.pdf
2860
Vedlegg 18 - NO-058-YM Rogfast Entreprise E03 YM-plan.pdf
1246
Vedlegg 2 - 03-B01-101.pdf
3626
Vedlegg 2.pdf
38701
Vedlegg 20 - NO-143-YM Overvåkningprogram Byfjorden ifb utfylling i sjø E03.pdf
405
Vedlegg 3.1-03-V01-401.pdf
2921
Vedlegg 3.2 - 03-V01-402..pdf
2521
Vedlegg 3.pdf
1450
Vedlegg 4- 03-V06-401. rev.pdf
134
Vedlegg 4.pdf
35604
Vedlegg 5 - NO-088-GEO.pdf
2124
Vedlegg 5.pdf
7526
Vedlegg 6.pdf
988
Vedlegg 6-NO-085-GEO E03 Utfylling i sjø Mekjarvik_E sjete.pdf
10745
Vedlegg 7 - Mekjarvik Sør _Reguleringsbestemmelser.pdf
138
Vedlegg 8 - Mekjarvik Sør _Konsekvensutredning med vedlegg.pdf
7762
Vedlegg 9 - Mekjarvik Sør _Planbeskrivelse.pdf
5634
Vedlegg fastmerkerapport.pdf
15627
Vedleggsliste _addendum 03_D1_E03.pdf
133
Print...
Close window