II.1.1)
Title attributed to the contract by the contracting entity:
Dnr 201384 Upphandling ramavtal totalentreprenader avseende om- och nybyggnation av mottagningsstationer för elkraftdistribution
II.1.2)
Type of contract and location of works, place of delivery or of performance
Works
Main site or location of works, place of delivery or of performance:
NUTS codeVästmanlands län
II.1.3)
Information about a public contract, a framework agreement or a dynamic purchasing system (DPS)
The notice involves the establishment of a framework agreement
II.1.4)
Information on framework agreement
Framework agreement with several operators
maximum number of participants to the framework agreement envisaged: 10
Duration of the framework agreement
Duration in months: 72
Justification for a framework agreement, the duration of which exceeds four years:
Estimated total value of purchases for the entire duration of the framework agreementEstimated cost excluding VAT: 500000000
SEK
Frequency and value of the contracts to be awarded:
II.1.5)
Short description of the contract or purchase(s)
Uppdragen avser om- och nybyggnation av mottagningsstationer för
elkraftdistribution. (0,4-145kV) Detta inkluderar bl.a. markarbeten,
byggnadsarbeten, elarbeten etc. Alla avrop kommer att göras som
totalentreprenader enligt ABT06 men i olika samverkansformer.
II.1.6)
Common procurement vocabulary (CPV)
Main vocabulary
31200000
Electricity distribution and control apparatus
II.1.7)
Information about Government Procurement Agreement (GPA)
The contract is covered by the Government Procurement Agreement (GPA):
no
II.1.8)
Information about lots
This contract is divided into lots:
no
II.1.9)
Information about variants
Variants will be accepted:
no
II.2)
Quantity or scope of the contract
II.2.1)
Total quantity or scope:
omfattningen avser om-och nybyggnation av mottagningsstationer för elkraftdistribution. (0,4-145kV) Alla avrop kommer att göras som totalentreprenader enligt ABT 06, men i olika samverkansformer.
Estimated cost excluding VAT: 500000000
SEK
II.2.2)
Information about options
Options: yes
Description of these options:
Inga optioner
II.2.3)
Information about renewals
This contract is subject to renewal: no
II.3)
Duration of the contract or time limit for completion
Starting 31.
12.
2016
Completion 31.
12.
2024