Modernisation Project, Electrification Programme

The contract includes design and build of the new Sydhavn Traction power Sub Station (TSS) including 25 KV cable tracée to neutralsection placed in “Sydhavns tunnellen”, as well as building, foundation work, drainage, earthwork, technical equipment, test and commision etc. The contract includes delivery and installation of a complete turn-key substation in operational condition.

2020-03-06 14:00:00

45232221-7  Transformatorunderstation


Banedanmark
Carsten Niebuhrs Gade 43
1577
København V
Danmark


https://www.bane.dk/

Publicerade annonser
05.Meddelande om upphandling – försörjningssektorerna (TED (v209)) 2020-01-20 23:11
    14. Rättelse (TED (v209)) 2020-02-17 16:11
    14. Rättelse (TED (v209)) 2020-02-25 16:11
Delkontrakt
Modernisation of Traction Power
Ytterligare information:
Dokument Dokument