Steam turbine
Västerås
Mälarenergi AB is planning to invest in a new combined heat and power (CHP)
plant with auxiliary systems and to modernise the existing plant in Västerås. The
Project consists of four main parts: A steam boiler of 150 MWth for combustion of
recycled wood fuel; A back-pressure steam turbine of about 55 MWe; A flue gas
treatment system including flue gas condensation and combustion air
moisturizing system with condensate cleaning; A fuel handling system to supply
the boiler with fuel.
This procurement (Dnr 2015/34) relates to steam turbine.
Back-pressure steam turbine of about 55 MWe.